A single-story retail shell on an infill corner lot with six tenant suites ranging from a 2,400 SF coffee bar to a 9,800 SF fitness studio, each with its own work letter. The general contractor needed the landlord shell priced separately from each tenant improvement so costs could be allocated across leases.

Location

Atlanta, GA

Size

31,000 SF shell, 6 TI suites

Estimated value

$7.8M

Estimate turnaround

4 business days

Scope estimated

What we measured and priced

  • 840 CY of concrete in footings, 31,000 SF slab-on-grade and 420 LF of loading dock and site walls
  • 128 tons of structural steel with bar joists and 31,000 SF of metal roof deck
  • 31,000 SF of mechanically fastened TPO roofing with 6 curb-mounted RTU openings
  • 640 LF of aluminum storefront with 18 entrance doors and 2 overhead coiling grilles
  • Shell demising walls to deck for 6 suites with 11,000 SF of EIFS and brick veneer on the street facades
  • Restaurant suite with 1,200 SF kitchen, 1,000 CFM Type I hood, grease interceptor and 38 plumbing fixtures
  • Fitness studio with 6,200 SF of rubber flooring, 2 shower rooms and a dedicated 20-ton RTU
  • Six TI electrical scopes totaling 1,600 A of tenant service, 720 fixtures and 44 low-voltage drops
  • 0.9 acre of site paving, 48 parking stalls, utilities and streetscape improvements

The estimating challenge

Six work letters drew the line between landlord and tenant work in six different places: one tenant took the suite as a cold dark shell, another expected the landlord to provide a finished ceiling and distributed HVAC. The drawings did not consistently show which items belonged to which party, and the restaurant suite's grease interceptor and Type I hood exhaust route affected shell slab and roof work. The contractor needed a single estimate the developer could use to allocate costs across leases, delivered in four business days.

The result

LEEDS built a work-letter matrix that assigned every line item to landlord shell, landlord TI allowance or tenant cost, then produced a shell estimate and six suite estimates that rolled up to one bid total. We flagged the grease interceptor and hood shaft as shell-phase items so they would be poured and framed before the slab closed. The contractor bid $7.8M and was selected on a negotiated basis. The matrix became the developer's lease allocation document, and no scope disputes surfaced between tenants and landlord during construction.

Gallery

Project imagery

Price a project like this one

Upload your plans and get a fixed quote within 2 business hours. Most estimates are delivered in 24–48 hours.