New clients save 30% on their first estimate

Claim the offer

Budget development · Cost control

Construction budgets that hold from approval through the final pay application

A budget approved on day one is only useful if it survives contact with the design, the market and the schedule. We develop the cost plan, convert it into a monthly cash flow, set escalation and contingency by risk instead of by habit, run value engineering when numbers drift, and track committed and actual cost so the forecast stays honest through close-out.

Cost plan to cash flowRisk-based contingencyTracked against actuals
4.9/5 from 180+ contractors
  • 5.0 Google
  • 4.9 Trustpilot
  • 4.9 Clutch
Calculator with office supplies on a desk
Two contractors in white hard hats inspecting plans together on a construction site
Architectural blueprints laid out with drafting pencils, a metal ruler and a drawing tube
±3%

average variance between controlled budgets and final cost across tracked projects

BR Bluebeam Revu
RD RSMeans Data
SE Sage Estimating
P Procore
ME Microsoft Excel

Scope of takeoff

Budget components we build and control

Every component has a documented basis, an owner and a reporting line in the monthly variance report.

Elemental cost plan

Project cost allocated across substructure, shell, interiors, services and site

$ / $/SFUniFormat structure benchmarked to similar projects

Trade budget breakdown

Cost plan converted to CSI divisions and bid packages for buyout

$ / %

Cash flow forecast

Monthly spend curve with retainage and payment terms applied

$/MO
Multi-story building wrapped in scaffolding under a blue sky

Escalation allowance

Price growth to bid date and to the midpoint of each trade's work

% / YR

Contingency register

Design, construction and owner contingencies set by weighted risk and released by milestone

$ / %

Allowances and provisional sums

Placeholder budgets for finishes, fixtures and equipment not yet selected

$ / LS

Value engineering options

Cost-saving alternatives with savings, schedule impact and design consequences

$

Design reconciliation

Cost impact review at each drawing issue with variance against the target

$ / %Quantity and rate check of changed scope

Buyout tracking

Bids and awards compared against trade budgets, with savings and overruns identified

$ / %
Total station on a tripod set up in front of a construction site with a tower crane

Committed and actual cost

Subcontract values, change orders, invoices and accruals tracked to date

$

Forecast to complete

Rolling projection of final cost including pending changes and risk

$

Schedule of values

Contract sum divided into billable lines aligned to the budget structure

$ / LS

Project types

Project types we estimate

The same measured-twice standard applies whether the scope is a tenant improvement or a ground-up campus.

Calculator with office supplies on a desk
01

Owner-led capital programs

Multi-story building wrapped in scaffolding under a blue sky
02

Design-bid-build with fixed funding

Total station on a tripod set up in front of a construction site with a tower crane
03

GMP and cost-plus contracts

Rusty rebar grid ready for a concrete pour
04

Multifamily projects with construction loans

Interior wood stud framing and ceiling joists lit by sunlight through new windows
05

Healthcare and higher education expansions

Modern commercial lobby with a stone reception desk, wood paneling and seating area
06

Phased tenant improvement programs

Two construction workers in hard hats reviewing plans on a tablet beside a steel structure on a jobsite
07

School bond-funded construction

Calculator with office supplies on a desk
08

Value engineering after over-budget bids

Process

How our estimating process works

Four steps from upload to a bid-ready estimate, with a senior estimator signing off before anything leaves our desk.

Upload plans and scope
  1. 1

    Step 1

    Upload plans and scope

    Send your drawings, specifications and bid invitation through the secure upload form. We confirm scope, deadline and a fixed price within two business hours.

  2. 2

    Step 2

    Digital quantity takeoff

    Estimators measure every item from calibrated plans in Bluebeam and PlanSwift, color-coding each layer so quantities can be traced back to the drawing.

  3. 3

    Step 3

    Pricing and labor

    Quantities are priced with location-adjusted material costs, crew productivity rates and equipment, then marked up to your overhead and profit targets.

  4. 4

    Step 4

    Senior review and delivery

    A second estimator audits quantities and pricing, documents assumptions and exclusions, and delivers your Excel workbook, PDF summary and marked-up plans.

Free quote

Get a fixed quote for this scope

Upload drawings or a plan link and tell us the bid date. A senior estimator confirms scope, price and delivery before any work starts.

  • Scope confirmation and a fixed price within two business hours
  • Most estimates delivered in 24–48 hours
  • Unlimited revisions until bid day
  • Plans stay confidential and are deleted on request

Prefer to talk? Call +1 (800) 555-0199 or email info@leedsestimating.com.

Plans and documents

Drop your plans here or browse

PDF, DWG, DXF, ZIP, PNG, JPG, JPEG, WEBP, XLS, XLSX, DOC, DOCX, CSV · up to 5 files · 4.0 MB total

Plans stay confidential. Reply within 2 business hours.

By the numbers

Measured twice, delivered on time

5,000+Projects estimated
24–48hTypical turnaround
40+Trade categories
98%Takeoff accuracy

Why LEEDS

Why contractors switch to LEEDS

An estimating desk that behaves like an extension of your team, not a software subscription.

Multi-story building wrapped in scaffolding under a blue sky
  • Budgets are structured so the same lines drive the cost plan, bid packages, schedule of values and monthly tracking, avoiding rework at each stage.

  • Escalation, contingency and allowances sit, on separate lines, so each risk can be monitored and released independently.

  • Contingency is set from a weighted risk register, instead of a flat percentage, and its draw-down is reported monthly.

  • Value engineering options show savings alongside, schedule impact and design consequences, not just a lower number.

Total station on a tripod set up in front of a construction site with a tower crane
  • Variance reports explain the cause of each movement, whether design change, market pricing or scope clarification.

  • Cash flow forecasts incorporate retainage and payment terms, and align to draw schedules your lender will accept.

  • Exports match your accounting codes, so budget tracking reconciles with Sage, Procore or your internal ledger.

Estimate types

What type of cost & budget estimating can you get?

Match the estimate to where your project is. Every option is priced as a flat fee before work begins.

01

Initial project budget

A cost plan reconciled to the owner's funding, covering hard and soft costs with explicit contingency.

Accuracy
Class 4: -20% / +30%
Turnaround
3-5 days
02

Design-phase budget update

A reconciliation of cost against the cost plan at schematic and design development milestones.

Accuracy
Class 3: -10% / +20%
Turnaround
3-4 days
03

Value engineering study

A set of ranked alternatives with savings, schedule effects and design consequences.

Accuracy
Savings estimated within 10%
Turnaround
4-6 days
04

Cash flow and funding schedule

A monthly spend forecast aligned to the construction schedule and loan draw requirements.

Accuracy
Aligned to schedule baseline
Turnaround
2 days
05

Budget tracking report

A monthly report comparing budget, commitments, actuals and forecast, with exceptions highlighted.

Accuracy
Reconciled to accounting
Turnaround
2 days per cycle

Overview

Budgeting is a process that continues after the number is approved

A construction budget starts as a cost plan: the total project cost divided across building elements and trades, with a stated basis for each line. It must reconcile to the owner's funding, so soft costs, owner-furnished equipment and financing sit alongside the hard cost. From there the plan is stress-tested against the design, with each drawing issue triggering a reconciliation of cost against target. Soft costs, owner-furnished items and permit and utility fees are listed separately, so the construction number is never compared with a total that includes them.

Control depends on separating the pieces that move for different reasons. Escalation reflects the market and the schedule. Contingency covers design uncertainty, unforeseen conditions and bidding variance, and should draw down as risks retire. Allowances cover scope not yet selected. Keeping these in separate lines means that a spike in steel pricing does not quietly consume the money meant for unforeseen soil conditions. Releasing contingency on schedule matters as much as setting it: unused funds returned at each milestone give owners room to make late scope decisions without requesting more money.

Once the project is bought out, the budget becomes a tracking tool: original budget, approved changes, committed cost, actual cost to date and forecast to complete. The schedule of values is built from the same structure, so payment applications reconcile directly with the budget and the owner always sees the likely final number. Reports are issued monthly in a one-page summary format, followed by supporting detail for any line that moved more than a set threshold, so executives read one page and project teams read the rest.

Deliverables

What's included in your estimate package

Every deliverable is formatted so it can go straight into a proposal, a purchase order or an owner report.

XLSX

Estimate workbook

Quantities, unit costs, labor hours and totals organized by CSI division, with subtotals, markups and a bid summary tab.

PDF

Marked-up plans

Color-coded takeoff drawings showing exactly where every measured quantity came from.

XLSX

Material procurement list

Consolidated material quantities with waste factors applied, ready to send to suppliers for quotes.

XLSX

Labor hours by task

Crew-based labor hours and productivity rates so you can check the schedule against the estimate.

PDF

Assumptions and exclusions log

Every clarification, allowance and exclusion documented so your proposal scope is defensible.

PDF

Bid summary sheet

A proposal-ready one-page summary with overhead, profit, bonds and contingency applied.

Reviews

What contractors say after their first bid with us

What general contractors, subcontractors and developers say after bidding with our numbers.

“I used to lose a whole weekend to takeoffs. Now I upload on Friday and have board counts, mud and tape, and paint gallons by Monday morning.”

Elena Vasquez

Owner, Vasquez Drywall & Paint · San Antonio, TX

CSI divisions

CSI MasterFormat divisions we cover

Estimates are organized by division so they drop straight into your cost codes and schedule of values.

01General Requirements
03Concrete
04Masonry
05Metals
06Wood, Plastics & Composites
07Thermal & Moisture Protection
08Openings
09Finishes
22Plumbing
23HVAC
26Electrical
31Earthwork
32Exterior Improvements

Highlighted divisions are the primary scope on this page.

FAQ

Cost & Budget Estimating FAQs

Straight answers on scope, turnaround, pricing and deliverables.

What is the difference between a cost estimate and a budget?

An estimate predicts what the work will cost based on the current design. A budget is the approved spending limit, usually built from an estimate plus soft costs, contingency and escalation. Managing a budget means comparing every new estimate, bid and change order against that limit and reporting the difference.

How do you set contingency?

We build a risk register listing design completeness, site unknowns, market volatility and scope clarity, assign a probability and cost range to each, and sum the expected values. The result is a contingency tied to specific risks, with milestones at which unused portions can be released back to the owner.

What is value engineering and when should it be done?

Value engineering examines design choices to reduce cost without sacrificing required function. It is most effective at schematic and design development, when changes are cheap. We rank options by savings, schedule effect and risk, so the design team can choose with full information. We keep each option's assumptions written down alongside.

Can you track budgets against actual costs?

Yes. Each month we reconcile commitments, invoices and approved changes against the budget and issue a variance report with a forecast to complete. Lines are aligned to your accounting codes, so the numbers agree with what your controller and lender see. Reports also show cost per SF for easy benchmarking.

How is a schedule of values prepared?

We divide the contract sum into billable lines that reflect the real structure of the work, front-loading nothing and using awarded subcontract values wherever they exist. The result supports accurate pay applications and ties directly to the budget, which keeps billing, cost and progress reporting consistent. Contractors can bill from it directly.

Do you produce cash flow forecasts for lenders?

Yes. We build a monthly spend curve from the baseline schedule, apply retainage and payment terms, and align the result to the lender's draw schedule. The forecast is updated each reporting cycle, so equity and loan funding requirements are known well before they fall due. Forecasts update whenever the schedule or retainage terms change.

Ready for a cost & budget estimating quote?

Upload your plans and get a fixed quote within 2 business hours. Most estimates are delivered in 24–48 hours.